The History of the Zambezi Bridge from
Namibia to Zambia: 1982 - 2004
Dr. Klaus Dierks
The Zambezi Bridge between Katima Mulilo in Namibia and
Sesheke in Zambia at Wenela is surely one of the most remarkable engineering structures in
the entire southern Africa. But, this bridge has also a historical connotation because
this bridge always has been a symbol for Namibias independence. The structure is the
corner stone and end point of the Walvis Bay to Ndola and Lubumbashi Corridor (Trans
Caprivi Corridor). The numerous economic problems,
which were facing Namibia before independence, were in many aspects caused by its unique
traffic situation. This traffic situation was characterised by its biased transport
infrastructure towards South Africa. Nakop as "Namibia's
gateway to the outside world" was a first order handicap for the country. Transport
activities constituted a major constraint on the development of the economy of Namibia
because this one-sided
transport situation made Namibia's economy highly dependent on South Africa. South Africa used
this noose or lifeline situation to hold Namibia at ransom. The only solution
was to open the country to the east and the north. The Trans-Caprivi-Corridor with a
bridge over the Zambezi River at Katima Mulilo would end Namibias noose
situation.
Before the independence of Namibia, the Zambezi Bridge
project was not furthermore followed up. But, with the arrival of independence for Namibia
on 21.03.1990 and in my capacity as an elected Member of Parliament and Deputy Minister of
Works, Transport and Communication, the realisation of the Trans-Caprivi Highway was one
of the top priorities for the Ministry of Transport, not only in regard to planning and
design, but also to the financing of the project. The ultimate cornerstone of the
Trans-Caprivi project was Bridge 508, the Zambezi Bridge between Namibia and Zambia (the
number 508 was allocated to this bridge according to the official Namibian Bridge Register
by myself in 1982). Without Bridge 508 the Walvis Bay Corridor would be incomplete. The
engineering planning went thus ahead since 1990. Since 1990 I conducted negotiations with
the German government for the funding of the Trans-Caprivi Highway and Bridge 508.
Finally, with the progress of the planning process, it was found that that the most
suitable bridge site was just a few metres within Zambia and on the basalt rocks of the
Katima Rapids, just five metres from the old border beacon of 1927 between the then South
West Africa and Northern Rhodesia (present-day Zambia), still visible today just at the
western abutment of the bridge.
The main reason for the siting of the bridge however was
of a financial nature. Namibia would not have qualified for a grant for this bridge, of
which the total costs are now 100 Million Namibia Dollar (approximately ten Million US
Dollar in 2002). Namibia would have qualified only for a soft loan, which would eventually
be repaid by future Namibian generations. But the government of Zambia, as a least
developed country, qualified for a grant. Therefore, I was able to convince the
German government and the German Kreditanstalt für Wiederaufbau (KfW) to
build the bridge just within Zambia. This would mean that the benefits for the Namibian
economy are still the same. This deal saves the Namibian taxpayer 50 Million Namibia
Dollars. At the end of 1998 the negotiating process was concluded and Consulting Engineers
(Gauff Consulting Engineers and VKE Namibia) were duly appointed to do the detail design
and prepare the bridge for tendering. At the beginning of 1999 when everything seemed to
be on course, a new obstacle arose. The German government froze all funds for the bridge
because Zambia had not honoured its old outstanding debts to Germany. I travelled in a
hurry to Germany and maintained that it would not be fair to punish Namibia
for Zambias sins. At the end I could convince the German Minister for Economic
Co-operation and Development and the parliamentarian Committee for Development to release
the funds and thus to save the project.
The contract for the Zambezi Bridge was allocated to
Concor South Africa and the German Hochtief in 2002 and the bridge was
completed within the tendered time schedule in April 2004 and within the tendered amount.
All the abutments and 18 piers were completed in April 2003. The total length of the
bridge is 900 metres, with 19 spans. It is built in a radius of 1 600 metres on the Katima
Rapids. The bridge is designed to withstand a 100 years Zambezi flood. The two
extraordinary floods of 2003 and 2004 have not affected the structural safety of the
bridge. The bridge decks were built according to the ingenious German bridge-building
method of Incremental Launching (Taktschiebe-Verfahren) according to
Baur-Leonhardt, which means that the entire bridge deck was built on the western bank
under factory conditions and then every segment of 31,4 metres length was pushed
hydraulically over the river. Every week since February 2003 witnessed the pushing or
launching of a segment, and at the end of 2003, the whole 900-metre deck structure was
pushed over the two abutments and the 18 piers on a curvature of 1 600 metres radius from
the Katima Mulilo bank to the Sesheke bank in Zambia. At the end, the deck structure had a
total mass of 13 000 metric tonnes which had to be pushed with a hydraulic force of 750
tonnes at an average speed of 10 metres an hour. The dimensions of the bridge had only a
tolerance of a few millimetres.
At the beginning of 2004, the deck had to be finally
pre-stressed for the design traffic loads. Other auxiliary works like the finishing off,
the handrails and other smaller work items were duly completed in March 2004. According to
the German resident engineer of Gauff Consulting Engineers, Mr. Bernhardt Streit, the
concrete built by Namibian and Zambian construction workers was of such a high quality
that one has to walk very far nowadays in Germany to find such high quality
concrete.
The two presidents, Dr. Sam Nujoma and Levy Mwanawasa, officially opened the Zambezi-Bridge on 13.05.2004 in Katima Mulilo.
Copyright of Photo: Namibia Roads Authority
Sunset at the Zambezi River at Katima
Mulilo: February 2003
Copyright of Photos: Dr. Klaus Dierks
View from Katima Mulilo (Caprivi Cabins):
View over the Zambezi River to Sesheke in Zambia: Caprivi Region: During the Rainy Season:
February 2003
Copyright of Photos: Dr. Klaus Dierks
Zambezi River Bridge (Bridge 508) between
Katima Mulilo and Sesheke in Zambia is built on the Katima Rapids near the Namibia/Zambia Border Beacon (17°28'29,29" south, 24°17'50,04" east) with
"S.W.A." (South West Africa) on West Side and "N.A." (Northern
Rhodesia) on East Side
Copyright of Photos: Dr. Klaus Dierks
Construction of the Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Built on Katima Rapids (The
Bridge is situated in Zambia, the West-Abutment is 10 m from Boundary Beacon between
Namibia and Zambia): Radius: 1 600 m: Total Length: 877, 40 m : 17 Spans @ 47,10 m
each with two End Spans @ 38,35 m: Total Width of Bridge: 10,10 m; Incremental Launching
of the Deck over the entire Bridge from West to East has still to take place: 18 Piers and
the West-Abutment have been completed: Progress on February, 12th 2003: View from West to
East: Construction Time: 24 Months as from April 2002: Costs: approx. 9
US $ Million: The Bridge is the last missing Link in the Walvis Bay Corridor from Walvis
Bay to Lubumbashi in the Democratic Republic of the Congo
Copyright of Photos: Dr. Klaus Dierks
Construction of the Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: The Eastern Abutment is
excavated and the Foundation Base is prepared: Progress on February, 12th 2003
Copyright of Photo: Dr. Klaus Dierks
Construction of the Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: The Piers were constructed
with the Aid of a Causeway from both Sides of the River with an Opening in the Middle of
the River of 100 m Width during the dry Season: The Causeway, which is in the Process to
be removed, consists of a Rockfilldam and Precast Culvert Sections: The Abutments and 18
Piers were built from the Causeway with the Assistance of Cofferdams, all on Spread
Footings, mostly on Hard Rock (Basalt) within the River (30 MPa Compression Strength; Max.
Height: 19,90 m above foundation, 14,40 m above Low Water, 2,60 m above Highwater (High
Flood with 100 Years Probability)): Progress on February, 12th 2003: View from East
to West
Copyright of Photos: Dr. Klaus Dierks
Construction of the Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Incremental Launching of the
Deck over the entire Bridge from West to East from West Abutment to East Abutment: First
Stage is to put the Reinforcement in to the Segment (Hollow Prestressed Beam 31,4 m long
and 10,10 m wide) in the "Reinforcing Bay"; Stage 2 (Day 1) sees the Erection of
the Shuttering for Ground slab and the two Webs of the Box Girder, after the assembled
Reinforcing has been shifted into the "Casting Bay"; At Stage 3 (Day 2) the
casting of the Ground Slab and the two Webs takes place; At Stage 4 (Day 3) the Shuttering
is partly removed and the Shuttering for the Top Slab is erected; Stage 5 (Day 4) sees the
Concreting of the Top Slab; Stage 6 (Day 5) is a Rest Day in order to provide for the
Hardening of the Concrete; At Stage 7 (Day 6) the Prestressing for the Construction Stage
of the Box Girder (3 Days Compression Strength of the Concrete: 32 MPa) takes place and at
Stage 8 (Day 7, momentary on Monday) the Launching of the 31,4 m Segment to the next
Position takes place.
Copyright of Photo: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Incremental Launching of the
Deck: After the finished Reinforcement has been moved from the Reinforcing Bay into the
Casting Bay, the Segment (31,4 m long) is casted and prestressed and ready to be pushed
into the "Casting Bay": Progress on February, 12th 2003: Seventh Stage: After
Reaching of the necessary Concrete Compression Strength (32 MPa; Ultimate Compression
Strength: 45 MPa) and the Prestressing, the first Segment is pushed forward by the Length
of one Segment over the Bridge Substructure (Abutment and Piers): When the First Segment
has reached the other End of the Bridge (East Abutment): 28 Segments @ 31,40 m each will
have been pushed
Copyright of Photo: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Incremental Launching of the
Deck: Seventh Stage: The Segment (31,4 m long) which is casted and prestressed and ready
to be pushed, needs for the Launching Process a "Launching Nose (Mass 60 Tons)"
in order to minimise Positive and Negative Bending Moments during the Launching Process:
Progress on February, 12th 2003:
Copyright of Photos: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Incremental Launching of the
Deck: Seventh Stage: The Segment No. 7 (31,4 m long) which was casted and prestressed and
is today pushed over Pier No. 7 with an average Launching Speed of 10 m/hour: View
on top of Pier 7 to the West (Katima Mulilo Side): Progress on May, 19th 2003:
Copyright of Photos: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Incremental Launching of the
Deck: Seventh Stage: The Segment No. 7 (31,4 m long) which was casted and prestressed and
is today pushed over Pier No. 7 with an average Launching Speed of 10 m/hour: View
on top of Pier 7 to the East (Sesheke Side) : Progress on May, 19th 2003:
Copyright of Photos: Dr. Klaus Dierks
The Reinforcing Steel in the Reinforcing
Bay will be pushed into the into the Casting Bay which is to be seen in the Foreground:
Progress: May 2003
Copyright of Photo: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: Incremental Launching of the
Deck: Seventh Stage: The Segment No. 7 (31,4 m long) which was casted and prestressed and
is today pushed over Pier No. 7 with an average Launching Speed of 10 m/hour: View
from the western Abutment: The total Deck Mass is currently 5 000 t: With a Friction Value
of 0,02% the Launching Force is 100 t (initially: 300t): At the End, with the total Length
of the Box Girder pushed over the River into the final Position, the total Deck Mass will
be 13 000 t with a Launching Force of 260 t (750 t): Progress on May, 19th
2003:
Copyright of Photo: Dr. Klaus Dierks
During the Launching Process the
Prestressing Strings have to be grouted from Time to Time: Progress: May 2003
Copyright of Photos: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: View to the East: Progress on
May, 19th 2003:
Copyright of Photos: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: View to the West: Progress on
May, 19th 2003:
Copyright of Photos: Dr. Klaus Dierks
Construction of Zambezi River Bridge
(Bridge 508) between Katima Mulilo and Sesheke in Zambia: View to the East from the Katima
Mulilo Side: The Box Girder Deck will reach the Sesheke Bank in August/September 2003:
After this Date the final Bridge Bearings have to be mounted and the entire Bridge has to
be prestressed for the Design Traffic Loads: The Bridge will be completed on Schedule and
opened to Traffic during April 2004
Copyright of Photo: Dr. Klaus Dierks
Dr. Klaus Dierks
06. May 2004